How to Avoid Overordering Concrete
Concrete trucks charge a short-load fee of $50โ$150 if you order less than their minimum (usually 3โ5 yards). So DIYers order extra "just in case" โ and end up paying for 1โ2 yards they don't need. At $150/yard, that's $150โ$300 wasted.
The fix: Calculate exactly, then add exactly 5% for waste โ no more. A 10ร10ร4" slab is 1.23 yards. At 5% waste: 1.30 yards. That's your number. Don't round up to 2.
If you're under the truck minimum, switch to bagged concrete. 80 lb bags yield 0.6 cubic feet each. For 1.30 yards (35 cubic feet), you need 59 bags. Bagged costs more per yard but there's no short-load fee and no waste from overordering.